Hi,
I'm trying to create time-based workflow that will trigger 90 days after an opportunity is created if there has been no activity on the opportunity for 30 days. I can't figure out how to set the criteria for workflow based on activities. Has anyone been able to do this? Thanks in advance for the help!
I'm trying to create time-based workflow that will trigger 90 days after an opportunity is created if there has been no activity on the opportunity for 30 days. I can't figure out how to set the criteria for workflow based on activities. Has anyone been able to do this? Thanks in advance for the help!
On the Opportunity Object you can get a handle to all the the necessary fields the you need to evaluate for your trigger:
Opportunity.IsClosed
Opportunity.CreatedDate
Opportunity.LastActivityDate
plus a Time Dependant Workflow = 90 Days After Created Date