Hi,

I'm currently facing an issue in computing for Case Milestone Target Date. I used calculateMilestoneTriggerTime method of MilestoneTriggerTimeCalculator interface to caluculate the trigger time. This method returns the value(in minutes) which will be added to the Case Milestone Start Date to get the Target Date. When I debug the value of Target Date it gives me the correct date and time, but the actual Target Date displayed on the Case Milestone page layout is different. Is there any other internal logic that is applied on top of the value output from this method?

Here are sample data:

1. Start Date : 2015-02-11 07:58:12
    Method Returns (in minutes) : 131048
    Target Date displayed on Debug Log: 2015-05-13 08:06:12
    Target Date displayed on UI : 2015-05-13 09:14

2.  Start Date : 2015-02-09 14:42:44
     Method Returns (in minutes) : 132191
     Target Date displayed on Debug Log: 2015-05-12 09:53:54
     Target Date displayed on UI : 2015-05-14 07:57