I am New to Salesforce,I don't Know How to Complete Below Trigger Scenario...PLZ help me to Complete below scenario...i will be highly oweful to you..


My Trigger Scenario:I have a object called "Project" having below Fields.
       ---->Project Name
       ---->Project Start Date
       ---->Project End Date
       ---->Total NO.of Hours( default value 100 hours )
       ---->Project Ratio(Picklist Data Type) having below values(Interms of Hours)
                --> 100-1
                --> 70-30    
                --> 50-50
                --> 30-70
                --> 0-100
Requirement:
------------
   If user selects Project Start Date And Project End Date,For Example User Select 2-3-2017 as Project Start Date and 20-9-2017 as Project End Date  and
       -->if user select "100-1" from picklist,total 100 hours(before Hyphen value) should be alloted to Project Start Date i.e "March" in this case.
       -->if user select "70-30" from picklist, 70 hours(before Hyphen value) should be alloted to Project Start Date i.e "March" in this case, remaining 30 Hours(after Hyphen Value) should be alloted to remaining months(In my case April,may,june,july,August,sep),we have to consider number of days in each month as well.
       -->if user select "50-50" from picklist, 50 hours(before Hyphen value) should be alloted to Project Start Date i.e "March" in this case, remaining 50 Hours(after Hyphen Value) should be alloted to remaining months(In my case April,may,june,july,August,sep),we have to consider number of days in each month as well.
       -->if user select "30-70" from picklist, 30 hours(before Hyphen value) should be alloted to Project Start Date i.e "March" in this case, remaining 70 Hours(after Hyphen Value) should be alloted to remaining months(In my case April,may,june,july,August,sep),we have to consider number of days in each month as well.
       -->if user select "0-100" from picklist,total 100 hours(After Hyphen value) should be alloted to Project End Date i.e "March" in this case.
After Completion of Above Requirement every Project Record should have a related list with below records:
       -->In Case Of "100-1" pick list Selection
           Record 1:March-100
           Record 2:April-0
           Record 3:May-0
           Record 4:June-0
           Record 5:July-0
           Record 6:AUgust-0
           Record 7:September-0

       -->In Case Of "30-70" pick list Selection
           Record 1:March-30
           For Remaining six records,70 hours should be devided to remaining Months ,we have to consider number of days in each month as well.
 
--------->Continue the above process for Remaing Pick List Selecton values As well.
please help me on this.........
I am New to Salesforce,I don't Know How to Complete Below Trigger Scenario...PLZ help me to Complete below scenario...i will be highly oweful to you..


My Trigger Scenario:I have a object called "Project" having below Fields.
       ---->Project Name
       ---->Project Start Date
       ---->Project End Date
       ---->Total NO.of Hours( default value 100 hours )
       ---->Project Ratio(Picklist Data Type) having below values(Interms of Hours)
                --> 100-1
                --> 70-30    
                --> 50-50
                --> 30-70
                --> 0-100
Requirement:
------------
   If user selects Project Start Date And Project End Date,For Example User Select 2-3-2017 as Project Start Date and 20-9-2017 as Project End Date  and
       -->if user select "100-1" from picklist,total 100 hours(before Hyphen value) should be alloted to Project Start Date i.e "March" in this case.
       -->if user select "70-30" from picklist, 70 hours(before Hyphen value) should be alloted to Project Start Date i.e "March" in this case, remaining 30 Hours(after Hyphen Value) should be alloted to remaining months(In my case April,may,june,july,August,sep),we have to consider number of days in each month as well.
       -->if user select "50-50" from picklist, 50 hours(before Hyphen value) should be alloted to Project Start Date i.e "March" in this case, remaining 50 Hours(after Hyphen Value) should be alloted to remaining months(In my case April,may,june,july,August,sep),we have to consider number of days in each month as well.
       -->if user select "30-70" from picklist, 30 hours(before Hyphen value) should be alloted to Project Start Date i.e "March" in this case, remaining 70 Hours(after Hyphen Value) should be alloted to remaining months(In my case April,may,june,july,August,sep),we have to consider number of days in each month as well.
       -->if user select "0-100" from picklist,total 100 hours(After Hyphen value) should be alloted to Project End Date i.e "March" in this case.
After Completion of Above Requirement every Project Record should have a related list with below records:
       -->In Case Of "100-1" pick list Selection
           Record 1:March-100
           Record 2:April-0
           Record 3:May-0
           Record 4:June-0
           Record 5:July-0
           Record 6:AUgust-0
           Record 7:September-0

       -->In Case Of "30-70" pick list Selection
           Record 1:March-30
           For Remaining six records,70 hours should be devided to remaining Months ,we have to consider number of days in each month as well.
 
--------->Continue the above process for Remaing Pick List Selecton values As well.
My Requirement is:
--->i have a check box filed on account named as joint account.
--->while creating new account  end user checkd that check box and saved the account record.
---->here is my main requirement part:if check box is checked user can able to create only 2 contacts for that particular account,if user trying to create third       contact it has to throw an error.
----->if check box is not checked user can able to create only 1 contact for that particular account,if user trying to create second contact it has to       throw an error.
How can we achieve above requirement i tried a lot but i am unsuccessful
I am New to Salesforce,I don't Know How to Complete Below Trigger Scenario...PLZ help me to Complete below scenario...i will be highly oweful to you..


My Trigger Scenario:I have a object called "Project" having below Fields.
       ---->Project Name
       ---->Project Start Date
       ---->Project End Date
       ---->Total NO.of Hours( default value 100 hours )
       ---->Project Ratio(Picklist Data Type) having below values(Interms of Hours)
                --> 100-1
                --> 70-30    
                --> 50-50
                --> 30-70
                --> 0-100
Requirement:
------------
   If user selects Project Start Date And Project End Date,For Example User Select 2-3-2017 as Project Start Date and 20-9-2017 as Project End Date  and
       -->if user select "100-1" from picklist,total 100 hours(before Hyphen value) should be alloted to Project Start Date i.e "March" in this case.
       -->if user select "70-30" from picklist, 70 hours(before Hyphen value) should be alloted to Project Start Date i.e "March" in this case, remaining 30 Hours(after Hyphen Value) should be alloted to remaining months(In my case April,may,june,july,August,sep),we have to consider number of days in each month as well.
       -->if user select "50-50" from picklist, 50 hours(before Hyphen value) should be alloted to Project Start Date i.e "March" in this case, remaining 50 Hours(after Hyphen Value) should be alloted to remaining months(In my case April,may,june,july,August,sep),we have to consider number of days in each month as well.
       -->if user select "30-70" from picklist, 30 hours(before Hyphen value) should be alloted to Project Start Date i.e "March" in this case, remaining 70 Hours(after Hyphen Value) should be alloted to remaining months(In my case April,may,june,july,August,sep),we have to consider number of days in each month as well.
       -->if user select "0-100" from picklist,total 100 hours(After Hyphen value) should be alloted to Project End Date i.e "March" in this case.
After Completion of Above Requirement every Project Record should have a related list with below records:
       -->In Case Of "100-1" pick list Selection
           Record 1:March-100
           Record 2:April-0
           Record 3:May-0
           Record 4:June-0
           Record 5:July-0
           Record 6:AUgust-0
           Record 7:September-0

       -->In Case Of "30-70" pick list Selection
           Record 1:March-30
           For Remaining six records,70 hours should be devided to remaining Months ,we have to consider number of days in each month as well.
 
--------->Continue the above process for Remaing Pick List Selecton values As well.
please help me on this.........
My Requirement is:
--->i have a check box filed on account named as joint account.
--->while creating new account  end user checkd that check box and saved the account record.
---->here is my main requirement part:if check box is checked user can able to create only 2 contacts for that particular account,if user trying to create third       contact it has to throw an error.
----->if check box is not checked user can able to create only 1 contact for that particular account,if user trying to create second contact it has to       throw an error.
How can we achieve above requirement i tried a lot but i am unsuccessful